Theme Park Queues and Cycle Time Reduction

rollercoasterWritten by Erica Bassford, Engagement Leader at LI Europe.

Have you visited any theme parks recently? Got tired feet from standing still for so long in the inevitable queues? On a recent visit, after 40 minutes of standing in a very long queue, waiting to ride the next fast and furious rollercoaster, my son turned to me and said “why do we have to wait so long Mum”?

I could have said, “Because there are lots of people waiting to go on this ride”, or “Because ‘Express tickets’ get to go ahead of us” or “We just have to wait our turn” – but I didn’t. Instead it got me thinking about Bottlenecks, Cycle Time Reduction and simple Throughput, which I decided to share with my son…

First we broke the activity down or mapped the cycle: open the entry gate, load people into seats, close safety harnesses, issue safety instructions over the tannoy, check safety harness, raise harness to move small riders to left hand side, lower safety harness again, ride, release safety harness, unload people, open exit gate, close exit gate – repeat. 

I then asked my son what ideas he had to make the queue quicker and he came up with the following four ways they could optimise the cycle:

  1. Why don’t they fill all the seats?
    My son had identified that they should keep the bottleneck full at all times because every missed unit is lost forever. (Some parks have adopted the ‘single rider’ lane to cover this but alas it was not the case at this park!) 
  2. They should tell you which side the children should sit before you get in so they don’t have to keep lifting the safety harness for people to switch!
    He even suggested a picture (or visual aid) to show which side the grownups should go and ensure clear instructions are given early to prevent waste on the bottleneck machine.
  3. The man who opens the exit gate keeps getting stuck behind the people trying to leave so it’s taking ages to open the gate and let everyone out. Why don’t they open the exit gate at the same time as the safety harness is raised?
    Good question. Why not introduce concurrent activities to shorten the cycle time?
  4. Could they move the start of the queue next to the entry gate, not at the top of the 15 steps down to the entry gate?
    He’d identified that they could start activities earlier to shorten the cycle time.

If we’d achieved nothing else – by the time we had developed our shortened cycle it was finally our turn and I didn’t have to hear him ask “Why do we have to wait so long” over and over again! It didn’t however, stop him from asking to buy a fastpass ticket!

Cycle Time Reduction is a powerful tool, with the ability to increase throughput on any repetitive cycle. Are you frustrated by lack of throughput in your plant? Get in touch for some ideas of how you could shorten the cycle.

Testimonials

A key learning for me was that delegation is as much about the development of others as it is removing an action from my list. I now think of delegation as an opportunity for my team to develop and try new things. The more I do it, the more effective it is. Delegation is now one of my key management tools.

Front Line Manager on Aspire Programme

I believe that the project has been the catalyst for some big changes in the way we operate and think. Your presence, support, enthusiasm and ability to engage the personnel involved has been integral to this.

Keith Bassett, Plant Manager, KR Castlemaine